Project Timeline




           *  December 2017 – Final investment decision – Award of   *  2020 – Removal of wellhead, riser, process and accom-
             major contracts                                       modation platforms
           *  October 2018 – First steel cut on process, wellhead and   *  2020 – Installation of jackets for accommodation plat-
             riser platforms                                       form and processing centre

           *  2017–2019 – Preparations for shut-in and redevelop-  *  2021 – Installation of new wellhead and riser platforms
             ment                                                  and jackets extended – Installation of new processing
                                                                   centre and accommodation platform
           * September 2019 – Shut-in of production
                                                                 * 2022 – First production at new Tyra facilities











































                SINCE THE PLANNING
                OF THE EXTENSIVE

                PROJECT BEGAN, IT
                HAS BEEN A FUNDA-

                MENTAL PRINCIPLE
                THAT WE WILL RE-USE

                WHAT WE CAN’




                Morten Hesselager Pedersen,
                VP and Head of Tyra redevelopment




                                                   25 / TYRA REDEVELOPMENT