Project Timeline
* December 2017 – Final investment decision – Award of * 2020 – Removal of wellhead, riser, process and accom-
major contracts modation platforms
* October 2018 – First steel cut on process, wellhead and * 2020 – Installation of jackets for accommodation plat-
riser platforms form and processing centre
* 2017–2019 – Preparations for shut-in and redevelop- * 2021 – Installation of new wellhead and riser platforms
ment and jackets extended – Installation of new processing
centre and accommodation platform
* September 2019 – Shut-in of production
* 2022 – First production at new Tyra facilities